Estimation and Costing MCQ

Q. 21 The following item of earth work is not measured separately.

A. Site clearance

B. Steps in deep excavation

C. Setting out of works

D. All the above

D. All the above


Q. 22 The measurement is made in square metre in case of

Estimation and Costing MCQ

A. Hollow concrete block wall

B. Cement concrete in foundation

C. R.C.C. structure

D. None of these

D. None of these


Q. 23 The area of the cross-section of a road fully in banking shown in the given figure, is

A. [sb² + r² (2bd + sd)²]/(r s)

B. [sb² + r² (2bd + sd)²]/(r² s²)

C. [sb² + r² (2bd + sd)²]/(r² s5)

D. None of these

C. [sb² + r² (2bd + sd)²]/(r² – s5)


Q. 24 Cost of fittings and their fixing is specified for the following sanitary fittings

A. Lavatory basins

B. Water closets

C. Flushing pipes

D. All the above

D. All the above


Q. 25 The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

A. Surface dressing

B. Cutting

C. Excavationc

D. Surface excavation

D. Surface excavation


Q. 26 For the construction of buildings, the subheads of the estimate are

A. Brickwork, Stone work, Roofing

B. Brickwork Flooring, Wood work, Steel work

C. Earthwork, Concrete work, Brick work

D. All the above

B. Fat lime


Q. 27 Pick up the correct statement from the following:

A. Glazing is measured in sq.m

B. Pointing is measured in sq.m

C. Plastering is measured in sq.m

D. All the above

D. All the above


Q. 28 Pick up the correct statement from the following:

A. Area of canal in cutting = BD + Sd2 where B = bed width, d = depth of cutting and S is the side slope

B. If F.S.L. is above N.S.L the canal is called partly in cutting and partly in filling and berms are designed as 2d where d is full supply depth

C. If the bed level is above N.S.L. the canal is called fully in baking and the berms are designed as 3 d where d is full supply depth of water (F.S.D.)

D. All the above

D. All the above


Q. 29 Pick up the incorrect statement from the following:

A. No deduction is made for volumes occupied by pipes, not exceeding 100 sq.cm in cross- section

B. No deduction is made for the volume occupied by reinforcement

C. No deduction is made for the openings upto 0.1 sq.m

D. None of these

D. None of these


Q. 30 The value of ‘B‘ of Indian type W.C. shown in the given figure is:

Estimation and Costing MCQ
Estimation and Costing MCQ 3

A. 30 cm

B. 45 cm

C. 50 cm

D. 25 cm

B. 45 cm


You May Also Like:

Civil Engineering MCQ

Share This Post

Download Construction Excel Sheet

Scroll to Top
DMCA.com Protection Status