Building Estimate

Building Estimate is processed of predicting the probable cost of the project by calculating material quantity and their costing with help of market rates before undertaking any construction project. Here, In this article, we will learn about how to do an Estimation of A Building With a Plan.


Detailed Estimation of Building with Plan pdf

The following steps to be followed to do an estimation of building with a plan,

Data Required Preparing Estimate

  • Plan, Elevation & section.
  • Schedule of the opening of doors and windows.
  • Foundation drawing.
  • Column & Beam drawings.

Read More: Building Estimation Excel Sheet Free Download


Estimation of Building

The following is the estimation and costing of building sample pdf

1. Interpretation of Drawing

Estimation of a Building with Plan

Before you directly start calculating quantity, you must precisely and correctly read the construction drawing.

  • Check dimension of each block is provided or not.
  • The check Schedule of the opening is there.
  • Check specification of work.
  • Check the thickness of the wall is same or changes.
  • Check Rise and tread dimension of the stair.
  • Check type of foundation and its details drawing.

2. Prepare Estimation Sheet

Following is a sample sheet for preparing the estimate.

While taking length, width, and depth/ height dimensions remember that not all dimensions are given in drawing. Some dimensions you need to calculate from drawing also.

3. Calculating Quantity

For example, a first quantity of the estimation sheet is an excavation in the foundation. To find out the dimension of length, width, and depth of excavation from drawing.

Building Estimation With Plan
Civil Work Estimate In Excel

Estimation of a Building with Plan pdf

Keep in Mind

  • Excavation depth is calculated from ground level to bottom of PCC work.
  • The size of the trench is larger than the size of the footing to provide easy for workers.

Here, the Size of footing is 1 m x 1 m. So, consider 0.25 m extra margins on both sides of the trench.

Length will be = 0.25 + 1 + 0.25 = 1.5 m, and Size becomes 1.5 m x 1.5 m. Depth is given 1.5 m from ground level.

Now, find the number of Footing in the building = 12 nos. Put all values in the Estimation sheet multiple with each other will gives you the quantity of excavation.

In a similar way, you can calculate other quantities like PCC, Footing Concrete; Earth filling, Plinth beam concrete, DPC, Brick Work in Superstructure, RCC Slab Concrete, etc.

Read More: Steel Quantity Calculation Excel Sheet


Building Estimation With Plan
Building Estimation With Plan

Free Download Building Estimate Format In Excel

Building Estimation With Plan
Building Estimation With Plan
Building Estimate | Building Estimate Format In Excel | Estimation and Costing of Building | Estimation of a Building with Plan pdf | Detailed Estimate of a Residential Building

Watch Full Video: Building Estimation With Plan

Building Estimation in Excel

FAQs

Building Estimation and Costing

Building estimation is determining the probable cost of buildings before the construction proceeds, in order to achieve success in the project. Building Estimation is also beneficial for passing tenders.

How do you estimate a building?

Excel Sheets, Online Valuation tools,  FHFA House Price Index Calculator, hiring experts, etc are some of the Estimation Tools. However, if you want the do it manually, it is necessary to simplify the whole estimation method into small parts and begin grom foundation.

How do I calculate building quantities?

Building Quantities can be calculated by choosing one of the following methods,
1. Center Line Method
2. Crossing method
3. Out to out and in to in a method
4. Bay method
5. Service unit method


You May Also Like

Share This Post

Leave a Reply


x

Related Posts

What Is PCC Concrete | Plain Cement Concrete | PCC In Construction | PCC Full Form | PCC Ratio | PCC Grades | PCC Meaning In Civil
What Is PCC Concrete? The term PCC refers to Plain Cement Concrete. PCC is the mixture of cement, fine aggregate(sand), and coarse aggregate ...
Cost of Construction of One Room | 10*10 room Construction Cost In India | Cost to Build 12x12 Room in India | 10×10 Room Estimate | One Room Construction Cost
10*10 room Construction Cost In India In this article, we will discuss what is the Cost of Construction of One Room or 10*10 Room Constructio...
Construction Manager Job Description | Construction Manager Duties | Construction Manager Responsibilities
Construction management is one of the crucial roles to play in any construction project. There are various construction management duties in pro...
powered by RelatedPosts
Scroll to Top
DMCA.com Protection Status